City of Lacey 2018 Street Overlay Project Begins

0 Shares

Submitted by City of Lacey

Work has begun on the City of Lacey’s 2018 Street Overlay Project. The project, primarily funded through the Transportation Benefit District (TBD) thanks to the support of Lacey voters, provides reconstruction and asphalt overlay of several Lacey streets. Motorist may experience traffic delays in project areas and access may be restricted to local traffic, at times. The contractor expects the project to last approximately three months.

The 2018 Street Overlay project includes improvements to Golf Club Road, 14th Avenue SE, 17th Avenue SE, 18th Avenue SE, 19th Avenue SE, 21st Avenue SE, Brunswick Street, Magnolia Street, 33rd Court SE, Stikes Loop, Stikes Court, and Stikes Drive.

For project details and updates, visit ci.lacey.wa.us/Project-Updates or contact Aubrey Collier, Design and Construction Manager, at ACollier@ci.lacey.wa.us or 360-438-2639.

 