Submitted by Port of Olympia
When construction of Swantown Marina began in 1983, A, B and C docks were the first docks built. Over the last 30 years, the docks have experienced normal wear and tear and require rehabilitation. This maintenance project will extend the docks’ safe service life and preserve their value as a recreation asset.
There will be no changes to the dock configuration.
Work begins in mid-November with completion anticipated in spring 2015. The Port planned the project for the winter months when dock usage is at its lowest point.
The public boat launch will remain open during the project.
The Commission awarded the construction contract to Massana Construction, Inc. in the amount of $809,434 plus sales tax. Total project costs are estimated at $1,041,265.